Skyports Drone Services, RWE, and Skyways have completed Germany’s first long-range drone delivery flights to offshore wind turbines at the Arkona wind farm.
The three-week trial saw Skyports’ team operate Skyways’ V2 aircraft on automated round trips of approximately 80 kilometres between RWE’s operation and maintenance base in Mukran Port, on the German island of Rügen, and the Arkona wind farm in the Baltic Sea.
Carrying up to 10 kilograms of cargo, the drone replaced a two-to-three-hour boat journey with a 30-minute flight. Once at the wind farm, the aircraft performed an automated delivery directly to the turbine nacelle before returning to base.

Alex Brown, CEO of Skyports Drone Services, told Zag Daily that the trial proves the growing readiness of drones for offshore logistics. “We’re very close,” Brown said, noting that frameworks are now in place across much of Europe for routine Beyond Visual Line of Sight (BVLOS) operations in low-risk airspace.
“It’s now down to getting the commercial and operating model right with the energy companies as we gear up to launch permanent services.”
Brown added that 2026 could be a “big year” for Skyports’ offshore delivery business as it moves into “steady state” operations.
During the Arkona flights, Skyports used its Light Unmanned Certificate (LUC), issued by the Irish Aviation Authority, to operate in Germany with approval from the Luftfahrt-Bundesamt federal agency. Brown described the regulatory collaboration as “smooth”, adding that both authorities visited the site to see the operation live.
The biggest operational challenge, he said, lay in perfecting the automated payload drop system. The drone had to transition from fixed-wing mode after a 40km flight, navigate precisely to the nacelle, drop the cargo, and return, all while maintaining the integrity of the turbine infrastructure and operating in high winds.
For RWE, one of the world’s largest renewable energy companies, the trial forms part of a wider effort to validate drones as a permanent component of offshore logistics. Vivek Trivedi, O&M Optimisation Manager at RWE, said the trial demonstrated a “whole new dimension of efficiency”.
Skyways, the Texas-based aircraft manufacturer behind the dual-hybrid V2, said the project showcased the aircraft’s long-range performance.

Brown added that offshore wind, oil and gas sites present strong commercial potential. “They’re high-value, hard-to-access and safety-focused,” he told Zag Daily. “Any downtime costs operators a lot of money.”
The Arkona trial builds on previous collaborations between Skyports and RWE, including BVLOS deliveries to offshore substations last year. Over the course of the latest trial, the Skyways aircraft flew more than 2,500 kilometres and logged over 65 hours of flight time.
With RWE now exploring how drones could form part of a hybrid supply chain alongside crew transfer vessels, Skyports believes that what began as a demonstration could soon become standard practice in offshore logistics.